City Council Announces Nearly $3 Million in Paving Projects for FY 2026

The City Council for the City of Pell City has approved a new paving project schedule for Fiscal Year 2026, authorizing the use of a $3 million capital improvement allocation to address a list of 47 streets and roads and covering a total of approximately 17.6 miles. The approval came during the council’s September 8, 2025, meeting via Resolution No. 2025-92.

The Pell City Street Department utilized a Pavement Condition Rating (PCR) system to prioritize which roads would be repaired or resurfaced. The system gave the highest priority to roads that showed the most degradation, or the largest drop in their PCR score, between 2021 and 2024.

“A PCR score is a third-party analysis of the roadway condition and points of failure,” City Manager Brian Muenger said.

A lower score indicates more cracking, potholes, and general surface deterioration. By comparing the 2021 score to the 2024 score, the city was able to identify which roads had declined the most and were most in need of immediate attention.

The preliminary road list was reviewed by Street Superintendent Greg Gossett and the paving contractor, Wiregrass Construction Company, Inc. The preliminary cost estimates currently do not include striping and other traffic markings.

Of note, City Manager Muenger indicated that any resurfacing work on Vaughan Road would occur at night, similar to the resurfacing of Industrial Park Drive in 2024.

Street NameBeginningEndingCost Estimate
10th Ave S19th St SPine Hill Rd$88,311.70
16th St N2nd AveCogswell Ave$16,600.89
16th St SCogswell Ave10th Ave S$83,478.51
17th StWhitesville RdCogswell Ave$63,635.33
19th St2nd Ave3rd Ave$16,685.33
1st Ave SDry Creek Rd23rd St$323,089.60
22nd StComer Ave4th Ave$32,975.40
27th St N12th AveDead End$21,826.52
2nd AveComer Ave16th St$66,453.87
2nd St NCogswell AveOld Wagon$27,340.90
36th St NComer Ave12th Ave$16,953.36
4th Ave N23rd StDead End$57,438.37
5th St NCogswell AveOld Wagon$13,680.72
6th St NOld Wagon3rd Ave$19,219.48
Addie LnHardwick LnDead End$19,565.47
Autumn CircleTraweek LnCul-De-Sac$13,335.83
Brown StreetWolf Creek RdBrown St$19,399.66
Bruce Etheridge Pkwy.19th St S231 S$132,762.79
Circle Dr EKay StDead End$33,766.75
Circle Dr SCircle Dr ECircle Dr S$21,538.50
Collins DrForrest DrDead End$27,354.76
Comer AveCogswell Ave231$47,644.35
Coosa StSmith RoadDead End$8,728.00
Eagle Point DrSunsetCul-De-Sac$88,747.52
Eagle Point LnEagle Point DrCul-De-Sac$71,690.02
Forest DrCollins DrDead End$5,454.32
Green AcresHoliday Est DrWindsor Dr$10,732.05
Hardwick LnDickey DrShelby Dr$33,222.83
Hilltop St9th AveDead End$20,674.75
Holiday Est DrHwy 231Dead End$60,720.11
Hunter Ridge LnPatches LnDead End$52,733.37
Hunting Ridge CirHunting Ridge DrHunting Ridge Dr$18,893.35
Hunting Ridge DrHwy 231Dead End$71,026.63
Kay StreetWolf Creek RdLakeview Dr$30,548.00
Lee RdPine Harbor RdEasonville Rd$115,931.34
Mallard DrJohnson DrDead End$27,647.36
Masters RoadHwy 34Dead End$105,241.38
Eagle Point CircleEagle Point LaneDead End$5,706.36
Nelson Dr33rd StAshley Dr$30,199.80
Old Collins Ferry RdForrest DrFunderburg Bend$67,642.00
Pleasant Valley DrCogswell AveOld Coal City$253,236.59
Seminole TrlOspery DrDead End$88,278.15
Thomason StPine Harbor RdLee Rd$38,831.15
Tyler StAshley DrBellview$10,848.58
Vaughan Ln (Night)Lewis Lake LnFlorida Rd$389,727.42
Whitesville RoadCogswell Ave17th St$99,588.22
Windsor DrGreen AcresDead End$24,971.53
Initial Total$2,894,078.91

Federal Paving Work on US 231 Causing Traffic Delays

We are aware of significant traffic delays currently being experienced by the public on US Highway 231 North.  This is due to an ongoing paving project being conducted by the Alabama Department of Transportation (ALDOT), who is responsible for the maintenance of State routes.

The paving work, which began near Dr. John Haynes Drive in Pell City, included the milling of existing asphalt, which has disabled the traffic signal loops, which detect the presence of vehicles and allow the signal to operate dynamically.  While the paving work itself is being conducted at night (after 7 p.m.), the impacted traffic signal loops cannot be repaired until the paving in this area is completed. This will unfortunately lead to continued traffic disruptions in the area for several more days.

MAP: 2024-2027 ALDOT Projects, Birmingham Regional Planning Commission

We understand the inconvenience this is causing. We have communicated the severity of these issues to ALDOT and have requested that they expedite the repair of the signal loops. 

Please exercise patience and consider utilizing alternate routes in the coming days to minimize delays. We will provide further updates as they become available, including a more precise timeline for the completion of the signal loop repairs.